Updating Linked Data in KAPPA-Workstation

There are two ways a linked gauge data may be updated in the KAPPA-Workstation (K-W) file:

  • Using the Update from Server option in Edit/QAQC: this is the simplest and the quickest way.

  • Dragging and dropping a gauge on an existing gauge in K-W and appending/replacing the gauge.

  1. Inside the K-W document, go to Edit/QAQC tab.

  2. Click on Update from Server, inl_update_from_server_icon.png,in the ribbon at the top.

    The dialog will list all the linked gauges in the K-W document:

    kw_linked_data_listed.png
  3. Select the gauges to update.

  4. Click on Update.

    If any new data, past the existing gauge data in the K-W document is found on the server, it will be appended to the gauge:

    kw_linked_data_updated.png